Within how long after each aerial application must the agricultural aircraft operation complete its written record?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 12039
- C: 72 hours
Explanation
Rule .1002(c) requires pilots and contractors to complete the written record within 72 hours of each application, unless a Pesticide Section employee requests it sooner for an incident investigation.
More questions: North Carolina Pesticide Law
- 12040Which item is part of the required aerial application record?
- 12041Within what time must an aerial contractor or pilot notify the Secretary of the Board of an emergency or accidental release of pesticide?
- 12042An aerial release is reported to the Pesticide Section. What must the report describe about the surrounding area?
- 12043May a pesticide be applied aerially while people who are not assisting in the application are in the target area?
- 12044What must an aerial pilot learn and confirm before application?
- 12045Under the aerial rules, how must the loading area be kept?